  "generated_at": "2026-10-06T16:50:59.317Z",
  "filings": [
    {
      "id": "filing-ercot-ma090926-01",
      "published_date": "2026-09-09",
      "source": "ercot_market_notice",
      "docket_or_forum": "ERCOT Market Notice",
      "title": "Batch Zero eligibility-verification RFIs issued",
      "summary": "ERCOT began issuing Batch Zero eligibility-verification RFIs on September 9, 2026. Complete responses are due within 10 Business Days of each RFI's issuance; an ILLE may request an extension of no more than five Business Days. Successful verification is required for inclusion in Batch Zero. RFI issuance does not establish final eligibility or authorize energization.",
      "importance": "high",
      "filing_type": "market_notice",
      "related_project_ids": [],
      "related_study_ids": [
        "study-process-batch-zero"
      ],
      "source_document_ids": [
        "ercot-ma090926-01"
      ],
      "confidence": "high"
    },
    {
      "id": "filing-ercot-mb091426-01",
      "published_date": "2026-09-14",
      "source": "ercot_market_notice",
      "docket_or_forum": "ERCOT Market Notice",
      "title": "State and Community Impact RFI issued",
      "summary": "ERCOT issued a separate State and Community Impact RFI to covered unenergized Batch Zero data-center facilities and reported substantiated medium-load data-center facilities of at least 25 MW and less than 75 MW. Complete responses are due October 12, 2026 at 5 p.m. CPT. This deadline applies to the community-impact RFI, not the separate eligibility-verification RFI; issuance is not final qualification or permission to energize.",
      "importance": "high",
      "filing_type": "market_notice",
      "related_project_ids": [],
      "related_study_ids": [
        "study-process-batch-zero"
      ],
      "source_document_ids": [
        "ercot-mb091426-01"
      ],
      "confidence": "high"
    },
    {
      "id": "filing-ercot-mc092126-01",
      "published_date": "2026-09-21",
      "source": "ercot_market_notice",
      "docket_or_forum": "ERCOT Market Notice",
      "title": "RIOO RFI visibility restrictions and public question guides",
      "summary": "ERCOT added RIOO controls restricting respondents' visibility of other submissions and posted question-reference guides for Batch Zero eligibility verification and the separate State and Community Impact RFI. The public guides describe questions, not respondent answers or completed verification.",
      "importance": "medium",
      "filing_type": "market_notice",
      "related_project_ids": [],
      "related_study_ids": [
        "study-process-batch-zero"
      ],
      "source_document_ids": [
        "ercot-mc092126-01"
      ],
      "confidence": "high"
    },
    {
      "id": "filing-ercot-mb091426-02",
      "published_date": "2026-09-24",
      "source": "ercot_market_notice",
      "docket_or_forum": "ERCOT Market Notice",
      "title": "Voluntary community-impact RFI option for newly substantiated medium loads",
      "summary": "ERCOT offered newly substantiated medium-load data-center customers voluntary State and Community Impact RFIs. The request cutoff was October 5, 2026; responses to issued RFIs remain due October 12, 2026 at 5 p.m. CPT. The voluntary option does not alter mandatory RFIs already issued to reported substantiated medium loads.",
      "importance": "high",
      "filing_type": "market_notice",
      "related_project_ids": [],
      "related_study_ids": [
        "study-process-batch-zero"
      ],
      "source_document_ids": [
        "ercot-mb091426-02"
      ],
      "confidence": "high"
    },
    {
      "id": "filing-ercot-ma090226-01",
      "published_date": "2026-09-02",
      "source": "ercot_market_notice",
      "docket_or_forum": "ERCOT Market Notice",
      "title": "Workshop to share proposed operational framework for implementing SB6-related Large Load curtailments, including registration requirements",
      "summary": "ERCOT announced an October 6, 2026 workshop on proposed SB6 large-load curtailment mechanics, registration and draft rule revisions. ERCOT is seeking stakeholder input before formal filing; these are proposals, not adopted requirements.",
      "importance": "medium",
      "filing_type": "market_notice",
      "related_project_ids": [],
      "related_study_ids": [],
      "source_document_ids": [
        "ercot-ma090226-01"
      ],
      "confidence": "high"
    },
    {
      "id": "filing-ercot-ma080326-04",
      "published_date": "2026-09-03",
      "source": "ercot_market_notice",
      "docket_or_forum": "ERCOT Market Notice",
      "title": "Batch Zero Conditional Classification issued to Transmission and/or Distribution Service Providers",
      "summary": "ERCOT issued provisional/conditional Batch Zero classifications to interconnecting DSPs/TSPs. Inclusion remains subject to verification, model-deficiency cures and any applicable PUCT good-cause exceptions. Failure to satisfy a condition may disqualify a load. Conditional inclusion does not authorize energization.",
      "importance": "high",
      "filing_type": "market_notice",
      "related_project_ids": [],
      "related_study_ids": [
        "study-process-batch-zero"
      ],
      "source_document_ids": [
        "ercot-ma080326-04"
      ],
      "confidence": "high"
    },
    {
      "id": "filing-ercot-mc090426-01",
      "published_date": "2026-09-04",
      "source": "ercot_market_notice",
      "docket_or_forum": "ERCOT Market Notice",
      "title": "RIOO Off-cycle Release",
      "summary": "ERCOT announced RIOO changes to support Batch Zero Verification and Community Impact RFIs and said issuance notices would follow. The notice does not establish that RFIs were issued or that verification was completed.",
      "importance": "medium",
      "filing_type": "market_notice",
      "related_project_ids": [],
      "related_study_ids": [
        "study-process-batch-zero"
      ],
      "source_document_ids": [
        "ercot-mc090426-01"
      ],
      "confidence": "high"
    },
    {
      "id": "filing-ercot-monthly-2026-01-large-load-status",
      "published_date": "2026-02-13",
      "source": "ercot_tac",
      "docket_or_forum": "ERCOT Monthly",
      "title": "January 2026 Large Load Interconnection Status Update",
      "summary": "ERCOT reported approximately 232,500 MW of proposed large load, 8,786 MW approved to energize, 3,977 MW observed peak demand, and 4,809 MW approved but not yet observed operational.",
      "importance": "high",
      "filing_type": "status_update",
      "related_project_ids": [
        "aggregate-ercot-large-load-queue-2026-01"
      ],
      "related_study_ids": [],
      "source_document_ids": [
        "ercot-monthly-2026-01"
      ],
      "confidence": "high"
    },
    {
      "id": "filing-ercot-llwg-2026-01-22-batch-zero",
      "published_date": "2026-01-22",
      "source": "ercot_llwg",
      "docket_or_forum": "LLWG",
      "title": "January LLWG materials identify Batch Zero, LLIS reform, VRT, and subsynchronous study workstreams",
      "summary": "The LLWG meeting materials list Batch Zero Loads, ERCOT Large Load Batch Studies, PGRR141, ride-through, and subsynchronous study materials as public workstreams.",
      "importance": "medium",
      "filing_type": "working_group_material",
      "related_project_ids": [],
      "related_study_ids": [
        "study-process-batch-zero",
        "study-process-lel-vrt-survey"
      ],
      "source_document_ids": [
        "ercot-llwg-2026-01-22"
      ],
      "confidence": "medium"
    },
    {
      "id": "filing-ma122325-02-workshop",
      "published_date": "2026-01-16",
      "source": "ercot_market_notice",
      "docket_or_forum": "PUCT 59142",
      "title": "ERCOT schedules public workshop for proposed Large Load Batch Study process framework",
      "summary": "ERCOT announced a February 3, 2026 workshop in connection with PUCT Project 59142 to propose a draft framework for a Large Load Batch Study process.",
      "importance": "medium",
      "filing_type": "market_notice",
      "related_project_ids": [],
      "related_study_ids": [
        "study-process-batch-study"
      ],
      "source_document_ids": [
        "ercot-ma122325-02",
        "puct-59142-index"
      ],
      "confidence": "high"
    },
    {
      "id": "filing-ma122325-03-workshop-update",
      "published_date": "2026-01-30",
      "source": "ercot_market_notice",
      "docket_or_forum": "PUCT 59142",
      "title": "ERCOT posts materials for February 3 Batch Study framework workshop",
      "summary": "ERCOT announced that materials had been posted for the February 3 public workshop on the proposed Batch Study framework.",
      "importance": "medium",
      "filing_type": "market_notice",
      "related_project_ids": [],
      "related_study_ids": [
        "study-process-batch-study"
      ],
      "source_document_ids": [
        "ercot-ma122325-03",
        "puct-59142-index"
      ],
      "confidence": "high"
    },
    {
      "id": "filing-ma122325-04-feedback",
      "published_date": "2026-02-03",
      "source": "ercot_market_notice",
      "docket_or_forum": "PUCT 59142",
      "title": "ERCOT requests stakeholder feedback on proposed Batch Study framework",
      "summary": "ERCOT requested stakeholder feedback from the February 3 workshop on the proposed Large Load Batch Study process framework.",
      "importance": "medium",
      "filing_type": "market_notice",
      "related_project_ids": [],
      "related_study_ids": [
        "study-process-batch-study"
      ],
      "source_document_ids": [
        "ercot-ma122325-04",
        "puct-59142-index"
      ],
      "confidence": "high"
    },
    {
      "id": "filing-mb030226-01-feedback",
      "published_date": "2026-03-02",
      "source": "ercot_market_notice",
      "docket_or_forum": "PUCT 59142",
      "title": "ERCOT requests feedback from February 26 Batch Study process workshop",
      "summary": "ERCOT requested stakeholder feedback from the February 26 workshop on a proposed framework for Large Load interconnection changes.",
      "importance": "medium",
      "filing_type": "market_notice",
      "related_project_ids": [],
      "related_study_ids": [
        "study-process-batch-study"
      ],
      "source_document_ids": [
        "ercot-mb030226-01",
        "puct-59142-index"
      ],
      "confidence": "high"
    },
    {
      "id": "filing-ma301326-01-batch-zero-comments",
      "published_date": "2026-03-13",
      "source": "ercot_market_notice",
      "docket_or_forum": "PUCT 59142",
      "title": "Stakeholder comments requested on proposed Large Load Batch Zero Process",
      "summary": "ERCOT tied PGRR145 and NPRR1325 to the proposed Batch Zero process for June 1, 2026 ERCOT Board consideration.",
      "importance": "high",
      "filing_type": "market_notice",
      "related_project_ids": [],
      "related_study_ids": [
        "study-process-batch-zero"
      ],
      "source_document_ids": [
        "ercot-ma301326-01",
        "puct-59142-index"
      ],
      "confidence": "high"
    },
    {
      "id": "filing-ercot-news-batch-zero-approved-2026-06-18",
      "published_date": "2026-06-18",
      "source": "ercot_large_load_page",
      "docket_or_forum": "PUCT 59142",
      "title": "PUCT approves ERCOT Batch Zero process for large-load interconnections",
      "summary": "ERCOT announced PUCT approval of Batch Zero and said applicant classifications are expected in August 2026, with a final statewide transmission plan expected in Fall 2027.",
      "importance": "high",
      "filing_type": "news_release",
      "related_project_ids": [],
      "related_study_ids": [
        "study-process-batch-zero"
      ],
      "source_document_ids": [
        "ercot-news-batch-zero-approved-2026-06-18",
        "ercot-pgrr145-batch-zero",
        "ercot-nprr1325-batch-zero"
      ],
      "confidence": "high"
    },
    {
      "id": "filing-ercot-mb062326-01-batch-zero-implementation",
      "published_date": "2026-06-23",
      "source": "ercot_market_notice",
      "docket_or_forum": "ERCOT Market Notice",
      "title": "ERCOT sets July 11 effective date for Batch Zero rules",
      "summary": "ERCOT stated that PGRR145 and NPRR1325 became effective July 11, 2026 and that the prior Planning Guide Section 9 Large Load Interconnection Study process remained in effect through July 10.",
      "importance": "high",
      "filing_type": "market_notice",
      "related_project_ids": [],
      "related_study_ids": [
        "study-process-batch-zero"
      ],
      "source_document_ids": [
        "ercot-mb062326-01",
        "ercot-pgrr145-batch-zero",
        "ercot-nprr1325-batch-zero"
      ],
      "confidence": "high"
    },
    {
      "id": "filing-ercot-tac-2026-03-large-load",
      "published_date": "2026-03-12",
      "source": "ercot_tac",
      "docket_or_forum": "TAC",
      "title": "March TAC report includes Large Load Interconnection status material",
      "summary": "The March TAC report includes Large Load Interconnection material, including public discussion of approvals over the prior twelve months.",
      "importance": "medium",
      "filing_type": "status_update",
      "related_project_ids": [
        "aggregate-ercot-large-load-queue-2026-01"
      ],
      "related_study_ids": [],
      "source_document_ids": [
        "ercot-tac-large-load-2026-03"
      ],
      "confidence": "medium"
    },
    {
      "id": "filing-ercot-board-2026-04-large-load",
      "published_date": "2026-04-01",
      "source": "ercot_board",
      "docket_or_forum": "ERCOT Board",
      "title": "April 2026 ERCOT Large Load Update presentation",
      "summary": "ERCOT posted a public April 2026 large-load update presentation with load-growth and process-reform context.",
      "importance": "medium",
      "filing_type": "status_update",
      "related_project_ids": [
        "aggregate-ercot-large-load-queue-2026-01"
      ],
      "related_study_ids": [],
      "source_document_ids": [
        "ercot-board-large-load-2026-04"
      ],
      "confidence": "medium"
    },
    {
      "id": "filing-ercot-ltlf-2026-04-15",
      "published_date": "2026-04-15",
      "source": "ercot_large_load_page",
      "docket_or_forum": "PUCT 58777",
      "title": "ERCOT preliminary 2026-2032 Long-Term Load Forecast filed for PUCT discussion",
      "summary": "ERCOT announced a preliminary 2032 demand forecast of approximately 367,790 MW and described TSP-provided medium and large load customer information as a key input.",
      "importance": "high",
      "filing_type": "forecast_filing",
      "related_project_ids": [],
      "related_study_ids": [
        "study-process-load-forecasting"
      ],
      "source_document_ids": [
        "ercot-news-ltlf-2026-04-15",
        "puct-58777-index"
      ],
      "confidence": "high"
    }
  ]
}