  "generated_at": "2026-07-15T16:02:00Z",
  "studies": [
    {
      "id": "study-process-load-information-form",
      "project_id": null,
      "study_type": "llis",
      "status": "submitted",
      "submitted_date": "2025-12-15",
      "review_start_date": null,
      "approved_date": null,
      "energization_target_date": null,
      "restudy_required": null,
      "source_document_ids": [
        "ercot-large-load-integration",
        "ercot-mb121525-01"
      ],
      "confidence": "high",
      "title": "Load Information Form established as the required LLIS intake document",
      "description": "ERCOT posted the Load Information Form and communication instructions for Section 9 Large Load Interconnection submissions."
    },
    {
      "id": "study-process-lel-vrt-survey",
      "project_id": null,
      "study_type": "vrt",
      "status": "submitted",
      "submitted_date": "2025-06-23",
      "review_start_date": null,
      "approved_date": null,
      "energization_target_date": null,
      "restudy_required": true,
      "source_document_ids": [
        "ercot-mb062325-01"
      ],
      "confidence": "high",
      "title": "Large Electronic Load VRT survey and model submission requirement",
      "description": "ERCOT required data center and crypto-mining Large Loads to provide DWG survey responses and dynamic models for voltage ride-through evaluation."
    },
    {
      "id": "study-process-final-ad-hoc-vrt",
      "project_id": null,
      "study_type": "vrt",
      "status": "under_ercot_review",
      "submitted_date": "2026-01-31",
      "review_start_date": null,
      "approved_date": null,
      "energization_target_date": "2026-06-30",
      "restudy_required": null,
      "source_document_ids": [
        "ercot-ma013126-01"
      ],
      "confidence": "high",
      "title": "Final ad hoc interim VRT assessment for pre-July 2026 energization",
      "description": "ERCOT offered a final ad hoc interim VRT assessment for eligible Large Loads requesting initial energization before July 1, 2026."
    },
    {
      "id": "study-process-far-west-no-solar",
      "project_id": null,
      "study_type": "llis",
      "status": "restudy_required",
      "submitted_date": "2026-02-23",
      "review_start_date": null,
      "approved_date": null,
      "energization_target_date": null,
      "restudy_required": true,
      "source_document_ids": [
        "ercot-ma022326-01"
      ],
      "confidence": "high",
      "title": "Far West Texas LLIS no-solar scenario requirement",
      "description": "ERCOT required TSPs to include a no-solar scenario for Large Load Interconnection Studies in identified Far West Texas counties."
    },
    {
      "id": "study-process-batch-study",
      "project_id": null,
      "study_type": "batch_study",
      "status": "under_ercot_review",
      "submitted_date": "2025-12-23",
      "review_start_date": "2026-01-01",
      "approved_date": null,
      "energization_target_date": null,
      "restudy_required": null,
      "source_document_ids": [
        "ercot-ma122325-01",
        "puct-59142-index"
      ],
      "confidence": "high",
      "title": "Large Load Batch Study process development",
      "description": "ERCOT initiated a stakeholder process to design a Batch Study process for Large Load interconnections."
    },
    {
      "id": "study-process-batch-zero",
      "project_id": null,
      "study_type": "batch_study",
      "status": "approved",
      "submitted_date": "2026-03-13",
      "review_start_date": "2026-03-13",
      "approved_date": "2026-06-18",
      "energization_target_date": null,
      "restudy_required": null,
      "source_document_ids": [
        "ercot-news-batch-zero-approved-2026-06-18",
        "ercot-mb062326-01",
        "ercot-pgrr145-batch-zero",
        "ercot-nprr1325-batch-zero",
        "ercot-batch-zero-readiness-faq-2026-07-10",
        "ercot-ma301326-01",
        "ercot-llwg-2026-01-22",
        "puct-59142-index"
      ],
      "confidence": "high",
      "title": "Large Load Batch Zero process approved and effective",
      "description": "The PUCT approved ERCOT's Batch Zero process on June 18, 2026; PGRR145 and NPRR1325 became effective July 11, 2026 after the prior Planning Guide Section 9 process ended July 10."
    },
    {
      "id": "study-process-load-forecasting",
      "project_id": null,
      "study_type": "forecasting",
      "status": "submitted",
      "submitted_date": "2026-04-15",
      "review_start_date": "2026-04-17",
      "approved_date": null,
      "energization_target_date": null,
      "restudy_required": null,
      "source_document_ids": [
        "ercot-news-ltlf-2026-04-15",
        "puct-58777-index"
      ],
      "confidence": "high",
      "title": "Preliminary 2026-2032 Long-Term Load Forecast filing",
      "description": "ERCOT filed a preliminary Long-Term Load Forecast for PUCT discussion, including large-load information provided by transmission and distribution companies."
    },
    {
      "id": "study-process-net-metering-review",
      "project_id": null,
      "study_type": "net_metering",
      "status": "under_ercot_review",
      "submitted_date": "2025-09-02",
      "review_start_date": "2025-09-02",
      "approved_date": null,
      "energization_target_date": null,
      "restudy_required": null,
      "source_document_ids": [
        "puct-58479-index",
        "ercot-large-load-integration"
      ],
      "confidence": "high",
      "title": "PUCT net-metering review path for co-located Large Load",
      "description": "PUCT Project 58479 tracks the rulemaking for net metering arrangements involving a Large Load co-located with an existing generation resource."
    }
  ]
}