title: "LCRA"
description: "LCRA: ERCOT generation developer with 9 projects on file (8 active, 0 commissioned, 1 dropped). 0.0% historical completion rate. Independent ERCOT developer track-record dossier by Matt Prusak."
canonical: "https://www.ercotqueue.com/developer/lcra"
markdown: "https://www.ercotqueue.com/developer/lcra.md"
resource_type: "developer"
source_report: "August 2026"
generated_at: "2026-09-08T19:34:08.442Z"
license: "https://creativecommons.org/licenses/by/4.0/"
---

# LCRA

LCRA is represented in ERCOTQueue as a developer filing-entity record.

## Track record

| Measure | Value |
| --- | ---: |
| Total historical projects | 9 |
| Active | 8 |
| Commissioned | 0 |
| Dropped | 1 |
| Historical completion rate | 0.0% |
| Portfolio capacity | 3.50 GW |
| Last observed activity | 2026-08 |

The historical completion rate is a backward-looking queue statistic. It does not establish the outcome of a current project.

## Historical project mix

| Fuel | Projects |
| --- | ---: |
| Gas | 9 |

## Projects in the current public report

| Project | INR | Fuel | Capacity | County | Stage | Build Chance |
| --- | --- | --- | ---: | --- | --- | ---: |
| [Sim Gideon Combined Cycle](https://www.ercotqueue.com/project/30INR0051.md) | 30INR0051 | Gas | 880.0 MW | Bastrop | Interconnection agreement; FIS pending | 90% |
| [Lost Pines Power Park](https://www.ercotqueue.com/project/30INR0052.md) | 30INR0052 | Gas | 880.0 MW | Bastrop | Interconnection agreement; FIS pending | 85% |
| [SCHNEIDER COMBINED CYCLE](https://www.ercotqueue.com/project/30INR0054.md) | 30INR0054 | Gas | 880.0 MW | Caldwell | Interconnection agreement; FIS pending | 88% |
| [SIM GIDEON GAS RICE](https://www.ercotqueue.com/project/31INR0011.md) | 31INR0011 | Gas | 226.0 MW | Bastrop | Interconnection agreement; FIS pending | 88% |
| [LOST PINES GAS RECIP](https://www.ercotqueue.com/project/29INR0166.md) | 29INR0166 | Gas | 113.0 MW | Bastrop | Interconnection agreement; FIS pending | 78% |
| [SCHNEIDER GAS RICE](https://www.ercotqueue.com/project/29INR0176.md) | 29INR0176 | Gas | 113.0 MW | Caldwell | Interconnection agreement; FIS pending | 86% |
| [LOST PINES GAS RECIP PHASE 2](https://www.ercotqueue.com/project/31INR0010.md) | 31INR0010 | Gas | 113.0 MW | Bastrop | Interconnection agreement; FIS pending | 83% |
| [SCHNEIDER GAS RICE PHASE 2](https://www.ercotqueue.com/project/31INR0013.md) | 31INR0013 | Gas | 113.0 MW | Caldwell | Interconnection agreement; FIS pending | 86% |

## Data

- Filing-entity scorecards: [https://www.ercotqueue.com/data/developer_scorecards.json](https://www.ercotqueue.com/data/developer_scorecards.json)
- Curated parent scorecards: [https://www.ercotqueue.com/data/developer_scorecards_parents.json](https://www.ercotqueue.com/data/developer_scorecards_parents.json)
- Developer-name change log: [https://www.ercotqueue.com/data/developer_changes.json](https://www.ercotqueue.com/data/developer_changes.json)

## Source, citation, and reuse

- Human-readable page: [LCRA](https://www.ercotqueue.com/developer/lcra)
- Markdown representation: [https://www.ercotqueue.com/developer/lcra.md](https://www.ercotqueue.com/developer/lcra.md)
- Source report: August 2026
- Site refresh: September 2026
- Methodology: [ERCOTQueue methodology](https://www.ercotqueue.com/methodology)
- License: [CC BY 4.0](https://creativecommons.org/licenses/by/4.0/)
- Source data (application/json): [https://www.ercotqueue.com/data/developer_scorecards.json](https://www.ercotqueue.com/data/developer_scorecards.json)

ERCOTQueue distinguishes reported source fields from independently derived analysis. Queue capacity records development and interconnection activity; it does not establish financing, construction, or commercial operation. Build Chance is a research signal, not a guarantee or investment recommendation.