# Crowded Star Solar

Crowded Star Solar is an ERCOT generation interconnection record identified by INR 20INR0241.

## Current reported project fields

| Field | Value |
| --- | --- |
| INR | 20INR0241 |
| Developer | [Jones City Solar, LLC](https://www.ercotqueue.com/developer/jones-city-solar-llc.md) |
| Fuel / technology | Solar / PV |
| Capacity | 218.8 MW |
| County | Jones County |
| ERCOT zone | WEST |
| Point of interconnection | tap 345kV 68001 Claytonville – 68004 Phantom Hill c2 (New Substation: Open Sky 68014) |
| Projected commercial-operation date | 2026-08-17 |
| Reported status | SS Completed, FIS Completed, IA |
| Funnel stage | Commissioned |

County is the public geographic precision used by ERCOTQueue. Map symbols are county-level evidence and are not exact project coordinates.

## Independently derived Build Chance

| Measure | Value |
| --- | ---: |
| Validation-selected Build Chance | 100% |
| P05 | 100% |
| P50 | 100% |
| P95 | 100% |

### Score factors

| Factor | Percentage-point contribution |
| --- | ---: |
| Stage base rate | +100.0 pp |
| Fuel adjustment | 0.0 pp |
| Developer-history adjustment | 0.0 pp |
| Stage-velocity adjustment | 0.0 pp |
| COD-slippage adjustment | 0.0 pp |
| FIS-progress adjustment | 0.0 pp |
| Capacity adjustment | 0.0 pp |

These factors are ERCOTQueue derivations. The displayed probability is not an ERCOT forecast or an official project status.

## Reported milestones

| Milestone | Date |
| --- | --- |
| screening started | 2019-01-21 |
| screening complete | 2019-04-19 |
| fis requested | 2019-05-22 |
| fis approved | 2024-11-05 |
| ia signed | 2019-12-17 |
| approved energization | 2026-04-22 |
| approved sync | 2026-05-28 |

## Observed monthly history

- First seen: 2019-05
- Last seen: 2026-08
- Appearances: 87
- Score-series basis: Monthly points use the as-of seven-factor raw model on the validation-selected raw scale because the current isotonic candidate did not pass the project-purged application guard. The final point is anchored to the published current project score. The series shows trajectory, not a previously published frozen forecast.

The 30 most recent observed changes are shown below. The public JSON contains the complete history.

| Report month | Change | Detail |
| --- | --- | --- |
| 2026-05 | Funnel stage | IA + FIS complete to Commissioned |
| 2026-04 | Projected COD | 2026-07-31 to 2026-08-17 (+1 month) |
| 2026-03 | Projected COD | 2026-07-08 to 2026-07-31 (0 months) |
| 2025-12 | Projected COD | 2026-06-20 to 2026-07-08 (+1 month) |
| 2025-08 | Projected COD | 2026-03-10 to 2026-06-20 (+3 months) |
| 2024-12 | Projected COD | 2025-12-31 to 2026-03-10 (+3 months) |
| 2024-11 | Funnel stage | IA signed, FIS pending to IA + FIS complete |
| 2024-05 | Projected COD | 2026-01-26 to 2025-12-31 (-1 month) |
| 2023-08 | Projected COD | 2025-12-31 to 2026-01-26 (+1 month) |
| 2023-03 | Projected COD | 2024-10-03 to 2025-12-31 (+14 months) |
| 2022-08 | Funnel stage | IA + FIS complete to IA signed, FIS pending |
| 2022-03 | Projected COD | 2023-10-03 to 2024-10-03 (+12 months) |
| 2021-11 | Funnel stage | IA signed, FIS pending to IA + FIS complete |
| 2021-10 | Projected COD | 2023-10-23 to 2023-10-03 (0 months) |
| 2021-04 | Projected COD | 2023-06-30 to 2023-10-23 (+4 months) |
| 2020-11 | Projected COD | 2022-12-15 to 2023-06-30 (+6 months) |
| 2020-09 | Funnel stage | IA + FIS complete to IA signed, FIS pending |
| 2020-08 | Projected COD | 2021-07-02 to 2022-12-15 (+17 months) |
| 2020-05 | Funnel stage | IA signed, FIS pending to IA + FIS complete |
| 2019-12 | Funnel stage | No IA to IA signed, FIS pending |
| 2019-08 | Funnel stage | IA signed, FIS pending to No IA |
| 2019-06 | Funnel stage | No IA to IA signed, FIS pending |
| 2019-05 | Funnel stage | First observation to No IA |

Complete project-history JSON: [https://www.ercotqueue.com/data/project_history/20INR0241.json](https://www.ercotqueue.com/data/project_history/20INR0241.json)

## Field provenance

- Reported fields: INR, name, developer, capacity, fuel, county, zone, point of interconnection, projected COD, status, and dated milestones.
- Derived fields: funnel stage, COD-delay indicators, Build Chance, factor contributions, and uncertainty range.
- Current project dataset: [https://www.ercotqueue.com/data/projects.json](https://www.ercotqueue.com/data/projects.json)
- Current flat CSV: [https://www.ercotqueue.com/data/projects.csv](https://www.ercotqueue.com/data/projects.csv)

## Source, citation, and reuse

- Human-readable page: [Crowded Star Solar](https://www.ercotqueue.com/project/20INR0241)
- Markdown representation: [https://www.ercotqueue.com/project/20INR0241.md](https://www.ercotqueue.com/project/20INR0241.md)
- Source report: August 2026
- Site refresh: September 2026
- Methodology: [ERCOTQueue methodology](https://www.ercotqueue.com/methodology)
- License: [CC BY 4.0](https://creativecommons.org/licenses/by/4.0/)
- Source data (application/json): [https://www.ercotqueue.com/data/projects.json](https://www.ercotqueue.com/data/projects.json)

ERCOTQueue distinguishes reported source fields from independently derived analysis. Queue capacity records development and interconnection activity; it does not establish financing, construction, or commercial operation. Build Chance is a research signal, not a guarantee or investment recommendation.