# Lumen Farm Solar SLF

Lumen Farm Solar SLF is an ERCOT generation interconnection record identified by INR 23INR0439.

## Current reported project fields

| Field | Value |
| --- | --- |
| INR | 23INR0439 |
| Developer | [Neches Solar, LLC](https://www.ercotqueue.com/developer/neches-solar-llc.md) |
| Fuel / technology | Solar / PV |
| Capacity | 201.0 MW |
| County | Anderson County |
| ERCOT zone | NORTH |
| Point of interconnection | Tap 138kV 3325 Blackburn Switch – 3272 Palestine |
| Projected commercial-operation date | 2028-09-30 |
| Reported status | SS Completed, FIS Started, No IA |
| Funnel stage | No interconnection agreement |

County is the public geographic precision used by ERCOTQueue. Map symbols are county-level evidence and are not exact project coordinates.

## Independently derived Build Chance

| Measure | Value |
| --- | ---: |
| Validation-selected Build Chance | 11% |
| P05 | 5% |
| P50 | 10% |
| P95 | 15% |

### Score factors

| Factor | Percentage-point contribution |
| --- | ---: |
| Stage base rate | +36.1 pp |
| Fuel adjustment | -0.7 pp |
| Developer-history adjustment | 0.0 pp |
| Stage-velocity adjustment | -10.0 pp |
| COD-slippage adjustment | -10.0 pp |
| FIS-progress adjustment | -4.5 pp |
| Capacity adjustment | 0.0 pp |

These factors are ERCOTQueue derivations. The displayed probability is not an ERCOT forecast or an official project status.

## Reported milestones

| Milestone | Date |
| --- | --- |
| screening started | 2022-01-06 |
| screening complete | 2022-03-31 |
| fis requested | 2021-12-29 |

## Observed monthly history

- First seen: 2022-01
- Last seen: 2026-08
- Appearances: 56
- Score-series basis: Monthly points use the as-of seven-factor raw model on the validation-selected raw scale because the current isotonic candidate did not pass the project-purged application guard. The final point is anchored to the published current project score. The series shows trajectory, not a previously published frozen forecast.

The 30 most recent observed changes are shown below. The public JSON contains the complete history.

| Report month | Change | Detail |
| --- | --- | --- |
| 2025-08 | Projected COD | 2026-06-30 to 2028-09-30 (+27 months) |
| 2025-06 | Projected COD | 2026-04-30 to 2026-06-30 (+2 months) |
| 2025-03 | Projected COD | 2026-03-13 to 2026-04-30 (+1 month) |
| 2023-01 | Projected COD | 2025-08-05 to 2026-03-13 (+7 months) |
| 2022-11 | Projected COD | 2024-12-31 to 2025-08-05 (+8 months) |
| 2022-10 | Developer field | Smokey Willie Solar to Neches Solar, LLC |
| 2022-09 | Projected COD | 2023-12-30 to 2024-12-31 (+12 months) |
| 2022-01 | Funnel stage | First observation to No IA |

Complete project-history JSON: [https://www.ercotqueue.com/data/project_history/23INR0439.json](https://www.ercotqueue.com/data/project_history/23INR0439.json)

## Field provenance

- Reported fields: INR, name, developer, capacity, fuel, county, zone, point of interconnection, projected COD, status, and dated milestones.
- Derived fields: funnel stage, COD-delay indicators, Build Chance, factor contributions, and uncertainty range.
- Current project dataset: [https://www.ercotqueue.com/data/projects.json](https://www.ercotqueue.com/data/projects.json)
- Current flat CSV: [https://www.ercotqueue.com/data/projects.csv](https://www.ercotqueue.com/data/projects.csv)

## Source, citation, and reuse

- Human-readable page: [Lumen Farm Solar SLF](https://www.ercotqueue.com/project/23INR0439)
- Markdown representation: [https://www.ercotqueue.com/project/23INR0439.md](https://www.ercotqueue.com/project/23INR0439.md)
- Source report: August 2026
- Site refresh: September 2026
- Methodology: [ERCOTQueue methodology](https://www.ercotqueue.com/methodology)
- License: [CC BY 4.0](https://creativecommons.org/licenses/by/4.0/)
- Source data (application/json): [https://www.ercotqueue.com/data/projects.json](https://www.ercotqueue.com/data/projects.json)

ERCOTQueue distinguishes reported source fields from independently derived analysis. Queue capacity records development and interconnection activity; it does not establish financing, construction, or commercial operation. Build Chance is a research signal, not a guarantee or investment recommendation.