# Val Vista Grid BESS 2

Val Vista Grid BESS 2 is an ERCOT generation interconnection record identified by INR 24INR0102.

## Current reported project fields

| Field | Value |
| --- | --- |
| INR | 24INR0102 |
| Developer | [Val Vista Grid, LLC](https://www.ercotqueue.com/developer/val-vista-grid-llc.md) |
| Fuel / technology | Battery / BA |
| Capacity | 210.6 MW |
| County | Hidalgo County |
| ERCOT zone | SOUTH |
| Point of interconnection | Tap 345kV 8383 North Edinburg - 80137 Stewart Road |
| Projected commercial-operation date | 2029-03-30 |
| Reported status | SS Completed, FIS Started, IA |
| Funnel stage | Interconnection agreement; FIS pending |

County is the public geographic precision used by ERCOTQueue. Map symbols are county-level evidence and are not exact project coordinates.

## Independently derived Build Chance

| Measure | Value |
| --- | ---: |
| Validation-selected Build Chance | 77% |
| P05 | 70% |
| P50 | 76% |
| P95 | 82% |

### Score factors

| Factor | Percentage-point contribution |
| --- | ---: |
| Stage base rate | +84.8 pp |
| Fuel adjustment | -2.9 pp |
| Developer-history adjustment | 0.0 pp |
| Stage-velocity adjustment | +5.0 pp |
| COD-slippage adjustment | -10.0 pp |
| FIS-progress adjustment | 0.0 pp |
| Capacity adjustment | +0.3 pp |

These factors are ERCOTQueue derivations. The displayed probability is not an ERCOT forecast or an official project status.

## Reported milestones

| Milestone | Date |
| --- | --- |
| screening started | 2021-10-01 |
| screening complete | 2021-12-09 |
| fis requested | 2021-10-01 |
| ia signed | 2025-12-31 |

## Observed monthly history

- First seen: 2021-10
- Last seen: 2026-08
- Appearances: 57
- Score-series basis: Monthly points use the as-of seven-factor raw model on the validation-selected raw scale because the current isotonic candidate did not pass the project-purged application guard. The final point is anchored to the published current project score. The series shows trajectory, not a previously published frozen forecast.

The 30 most recent observed changes are shown below. The public JSON contains the complete history.

| Report month | Change | Detail |
| --- | --- | --- |
| 2026-02 | Projected COD | 2028-06-01 to 2029-03-30 (+9 months) |
| 2026-01 | Funnel stage | No IA to IA signed, FIS pending |
| 2023-11 | Projected COD | 2026-06-01 to 2028-06-01 (+24 months) |
| 2023-05 | Projected COD | 2024-05-03 to 2026-06-01 (+25 months) |
| 2022-07 | Developer field | Monte Cristo Grid, LLC to Val Vista Grid, LLC |
| 2021-10 | Funnel stage | First observation to No IA |

Complete project-history JSON: [https://www.ercotqueue.com/data/project_history/24INR0102.json](https://www.ercotqueue.com/data/project_history/24INR0102.json)

## Field provenance

- Reported fields: INR, name, developer, capacity, fuel, county, zone, point of interconnection, projected COD, status, and dated milestones.
- Derived fields: funnel stage, COD-delay indicators, Build Chance, factor contributions, and uncertainty range.
- Current project dataset: [https://www.ercotqueue.com/data/projects.json](https://www.ercotqueue.com/data/projects.json)
- Current flat CSV: [https://www.ercotqueue.com/data/projects.csv](https://www.ercotqueue.com/data/projects.csv)

## Source, citation, and reuse

- Human-readable page: [Val Vista Grid BESS 2](https://www.ercotqueue.com/project/24INR0102)
- Markdown representation: [https://www.ercotqueue.com/project/24INR0102.md](https://www.ercotqueue.com/project/24INR0102.md)
- Source report: August 2026
- Site refresh: September 2026
- Methodology: [ERCOTQueue methodology](https://www.ercotqueue.com/methodology)
- License: [CC BY 4.0](https://creativecommons.org/licenses/by/4.0/)
- Source data (application/json): [https://www.ercotqueue.com/data/projects.json](https://www.ercotqueue.com/data/projects.json)

ERCOTQueue distinguishes reported source fields from independently derived analysis. Queue capacity records development and interconnection activity; it does not establish financing, construction, or commercial operation. Build Chance is a research signal, not a guarantee or investment recommendation.