title: "Utley Solar"
description: "Utley Solar: 222 MW Solar project in Freestone County, ERCOT NORTH developed by Palmera Solar Development, LLC. Currently IA, FIS pending; build-chance 78%. Independent ERCOT queue tracking by Matt Prusak."
canonical: "https://www.ercotqueue.com/project/24INR0117"
markdown: "https://www.ercotqueue.com/project/24INR0117.md"
resource_type: "project"
source_report: "July 2026"
generated_at: "2026-08-07T17:27:53.695Z"
license: "https://creativecommons.org/licenses/by/4.0/"
---

# Utley Solar

Utley Solar is an ERCOT generation interconnection record identified by INR 24INR0117.

## Current reported project fields

| Field | Value |
| --- | --- |
| INR | 24INR0117 |
| Developer | [Palmera Solar Development, LLC](https://www.ercotqueue.com/developer/palmera-solar-development-llc.md) |
| Fuel / technology | Solar / PV |
| Capacity | 221.8 MW |
| County | Freestone County |
| ERCOT zone | NORTH |
| Point of interconnection | Tap 345kV 3381 Big Brown Switch - 3391 Jewett |
| Projected commercial-operation date | 2028-05-11 |
| Reported status | SS Completed, FIS Started, IA |
| Funnel stage | Interconnection agreement; FIS pending |

County is the public geographic precision used by ERCOTQueue. Map symbols are county-level evidence and are not exact project coordinates.

## Independently derived Build Chance

| Measure | Value |
| --- | ---: |
| Validation-selected Build Chance | 78% |
| P05 | 71% |
| P50 | 77% |
| P95 | 83% |

### Score factors

| Factor | Percentage-point contribution |
| --- | ---: |
| Stage base rate | +83.9 pp |
| Fuel adjustment | -0.6 pp |
| Developer-history adjustment | 0.0 pp |
| Stage-velocity adjustment | +5.0 pp |
| COD-slippage adjustment | -10.0 pp |
| FIS-progress adjustment | 0.0 pp |
| Capacity adjustment | +0.1 pp |

These factors are ERCOTQueue derivations. The displayed probability is not an ERCOT forecast or an official project status.

## Reported milestones

| Milestone | Date |
| --- | --- |
| screening started | 2021-09-07 |
| screening complete | 2021-11-29 |
| fis requested | 2022-03-09 |
| ia signed | 2025-12-18 |

## Observed monthly history

- First seen: 2022-03
- Last seen: 2026-07
- Appearances: 52
- Score-series basis: Monthly points use the as-of seven-factor raw model on the validation-selected raw scale because the current isotonic candidate did not pass the project-purged application guard. The final point is anchored to the published current project score. The series shows trajectory, not a previously published frozen forecast.

The 30 most recent observed changes are shown below. The public JSON contains the complete history.

| Report month | Change | Detail |
| --- | --- | --- |
| 2026-01 | Projected COD | 2027-09-30 to 2028-05-11 (+8 months) |
| 2026-01 | Developer field | Palmera Solar Development LLC to Palmera Solar Development, LLC |
| 2026-01 | Funnel stage | No IA to IA signed, FIS pending |
| 2024-03 | Projected COD | 2025-04-15 to 2027-09-30 (+29 months) |
| 2022-11 | Projected COD | 2025-02-14 to 2025-04-15 (+2 months) |
| 2022-10 | Projected COD | 2024-04-15 to 2025-02-14 (+10 months) |
| 2022-03 | Funnel stage | First observation to No IA |

Complete project-history JSON: [https://www.ercotqueue.com/data/project_history/24INR0117.json](https://www.ercotqueue.com/data/project_history/24INR0117.json)

## Field provenance

- Reported fields: INR, name, developer, capacity, fuel, county, zone, point of interconnection, projected COD, status, and dated milestones.
- Derived fields: funnel stage, COD-delay indicators, Build Chance, factor contributions, and uncertainty range.
- Current project dataset: [https://www.ercotqueue.com/data/projects.json](https://www.ercotqueue.com/data/projects.json)
- Current flat CSV: [https://www.ercotqueue.com/data/projects.csv](https://www.ercotqueue.com/data/projects.csv)

## Source, citation, and reuse

- Human-readable page: [Utley Solar](https://www.ercotqueue.com/project/24INR0117)
- Markdown representation: [https://www.ercotqueue.com/project/24INR0117.md](https://www.ercotqueue.com/project/24INR0117.md)
- Source report: July 2026
- Site refresh: August 2026
- Methodology: [ERCOTQueue methodology](https://www.ercotqueue.com/methodology)
- License: [CC BY 4.0](https://creativecommons.org/licenses/by/4.0/)
- Source data (application/json): [https://www.ercotqueue.com/data/projects.json](https://www.ercotqueue.com/data/projects.json)

ERCOTQueue distinguishes reported source fields from independently derived analysis. Queue capacity records development and interconnection activity; it does not establish financing, construction, or commercial operation. Build Chance is a research signal, not a guarantee or investment recommendation.