# Panther Creek 1 Repower

Panther Creek 1 Repower is an ERCOT generation interconnection record identified by INR 24INR0578.

## Current reported project fields

| Field | Value |
| --- | --- |
| INR | 24INR0578 |
| Developer | [Panther Creek Wind Farm I&II, LLC](https://www.ercotqueue.com/developer/panther-creek-wind-farm-i-ii-llc.md) |
| Fuel / technology | Wind / WT |
| Capacity | 11.0 MW |
| County | Glasscock County |
| ERCOT zone | WEST |
| Point of interconnection | 1058 Longshore 345kV |
| Projected commercial-operation date | 2026-12-31 |
| Reported status | SS Completed, FIS Completed, No IA |
| Funnel stage | Commissioned |

County is the public geographic precision used by ERCOTQueue. Map symbols are county-level evidence and are not exact project coordinates.

## Independently derived Build Chance

| Measure | Value |
| --- | ---: |
| Validation-selected Build Chance | 100% |
| P05 | 100% |
| P50 | 100% |
| P95 | 100% |

### Score factors

| Factor | Percentage-point contribution |
| --- | ---: |
| Stage base rate | +100.0 pp |
| Fuel adjustment | 0.0 pp |
| Developer-history adjustment | 0.0 pp |
| Stage-velocity adjustment | 0.0 pp |
| COD-slippage adjustment | 0.0 pp |
| FIS-progress adjustment | 0.0 pp |
| Capacity adjustment | 0.0 pp |

These factors are ERCOTQueue derivations. The displayed probability is not an ERCOT forecast or an official project status.

## Reported milestones

| Milestone | Date |
| --- | --- |
| screening started | 2023-06-28 |
| screening complete | 2023-09-21 |
| fis requested | 2023-06-21 |
| fis approved | 2024-05-03 |
| approved sync | 2024-10-02 |

## Observed monthly history

- First seen: 2023-06
- Last seen: 2026-08
- Appearances: 39
- Score-series basis: Monthly points use the as-of seven-factor raw model on the validation-selected raw scale because the current isotonic candidate did not pass the project-purged application guard. The final point is anchored to the published current project score. The series shows trajectory, not a previously published frozen forecast.

The 30 most recent observed changes are shown below. The public JSON contains the complete history.

| Report month | Change | Detail |
| --- | --- | --- |
| 2026-07 | Projected COD | 2026-03-01 to 2026-12-31 (+9 months) |
| 2025-11 | Projected COD | 2025-09-01 to 2026-03-01 (+6 months) |
| 2025-05 | Projected COD | 2025-04-01 to 2025-09-01 (+5 months) |
| 2025-01 | Projected COD | 2024-12-31 to 2025-04-01 (+4 months) |
| 2024-10 | Funnel stage | No IA to Commissioned |
| 2024-08 | Projected COD | 2024-10-30 to 2024-12-31 (+2 months) |
| 2024-01 | Projected COD | 2024-05-31 to 2024-10-30 (+5 months) |
| 2023-06 | Funnel stage | First observation to No IA |

Complete project-history JSON: [https://www.ercotqueue.com/data/project_history/24INR0578.json](https://www.ercotqueue.com/data/project_history/24INR0578.json)

## Field provenance

- Reported fields: INR, name, developer, capacity, fuel, county, zone, point of interconnection, projected COD, status, and dated milestones.
- Derived fields: funnel stage, COD-delay indicators, Build Chance, factor contributions, and uncertainty range.
- Current project dataset: [https://www.ercotqueue.com/data/projects.json](https://www.ercotqueue.com/data/projects.json)
- Current flat CSV: [https://www.ercotqueue.com/data/projects.csv](https://www.ercotqueue.com/data/projects.csv)

## Source, citation, and reuse

- Human-readable page: [Panther Creek 1 Repower](https://www.ercotqueue.com/project/24INR0578)
- Markdown representation: [https://www.ercotqueue.com/project/24INR0578.md](https://www.ercotqueue.com/project/24INR0578.md)
- Source report: August 2026
- Site refresh: September 2026
- Methodology: [ERCOTQueue methodology](https://www.ercotqueue.com/methodology)
- License: [CC BY 4.0](https://creativecommons.org/licenses/by/4.0/)
- Source data (application/json): [https://www.ercotqueue.com/data/projects.json](https://www.ercotqueue.com/data/projects.json)

ERCOTQueue distinguishes reported source fields from independently derived analysis. Queue capacity records development and interconnection activity; it does not establish financing, construction, or commercial operation. Build Chance is a research signal, not a guarantee or investment recommendation.