# SERENGETI SOLAR

SERENGETI SOLAR is an ERCOT generation interconnection record identified by INR 25INR0227.

## Current reported project fields

| Field | Value |
| --- | --- |
| INR | 25INR0227 |
| Developer | [Abei Energy Green XIV LLC](https://www.ercotqueue.com/developer/abei-energy-green-xiv-llc.md) |
| Fuel / technology | Solar / PV |
| Capacity | 76.2 MW |
| County | Delta County |
| ERCOT zone | NORTH |
| Point of interconnection | Tap 138kV Enloe Tap (bus# 11806) – Delta sub (bus# 1802) |
| Projected commercial-operation date | 2028-09-18 |
| Reported status | SS Completed, FIS Completed, IA |
| Funnel stage | Interconnection agreement and FIS complete |

County is the public geographic precision used by ERCOTQueue. Map symbols are county-level evidence and are not exact project coordinates.

## Independently derived Build Chance

| Measure | Value |
| --- | ---: |
| Validation-selected Build Chance | 78% |
| P05 | 73% |
| P50 | 77% |
| P95 | 82% |

### Score factors

| Factor | Percentage-point contribution |
| --- | ---: |
| Stage base rate | +91.9 pp |
| Fuel adjustment | -0.6 pp |
| Developer-history adjustment | 0.0 pp |
| Stage-velocity adjustment | -2.3 pp |
| COD-slippage adjustment | -10.0 pp |
| FIS-progress adjustment | 0.0 pp |
| Capacity adjustment | -0.9 pp |

These factors are ERCOTQueue derivations. The displayed probability is not an ERCOT forecast or an official project status.

## Reported milestones

| Milestone | Date |
| --- | --- |
| screening started | 2022-12-07 |
| screening complete | 2023-03-06 |
| fis requested | 2022-11-18 |
| fis approved | 2026-04-03 |
| ia signed | 2025-12-30 |

## Observed monthly history

- First seen: 2022-12
- Last seen: 2026-07
- Appearances: 44
- Score-series basis: Monthly points use the as-of seven-factor raw model on the validation-selected raw scale because the current isotonic candidate did not pass the project-purged application guard. The final point is anchored to the published current project score. The series shows trajectory, not a previously published frozen forecast.

The 30 most recent observed changes are shown below. The public JSON contains the complete history.

| Report month | Change | Detail |
| --- | --- | --- |
| 2026-07 | Projected COD | 2028-04-20 to 2028-09-18 (+5 months) |
| 2026-04 | Funnel stage | IA signed, FIS pending to IA + FIS complete |
| 2026-02 | Funnel stage | No IA to IA signed, FIS pending |
| 2025-08 | Projected COD | 2027-09-13 to 2028-04-20 (+7 months) |
| 2024-12 | Projected COD | 2026-09-14 to 2027-09-13 (+12 months) |
| 2023-10 | Projected COD | 2026-10-07 to 2026-09-14 (-1 month) |
| 2023-09 | Projected COD | 2025-12-30 to 2026-10-07 (+10 months) |
| 2022-12 | Funnel stage | First observation to No IA |

Complete project-history JSON: [https://www.ercotqueue.com/data/project_history/25INR0227.json](https://www.ercotqueue.com/data/project_history/25INR0227.json)

## Field provenance

- Reported fields: INR, name, developer, capacity, fuel, county, zone, point of interconnection, projected COD, status, and dated milestones.
- Derived fields: funnel stage, COD-delay indicators, Build Chance, factor contributions, and uncertainty range.
- Current project dataset: [https://www.ercotqueue.com/data/projects.json](https://www.ercotqueue.com/data/projects.json)
- Current flat CSV: [https://www.ercotqueue.com/data/projects.csv](https://www.ercotqueue.com/data/projects.csv)

## Source, citation, and reuse

- Human-readable page: [SERENGETI SOLAR](https://www.ercotqueue.com/project/25INR0227)
- Markdown representation: [https://www.ercotqueue.com/project/25INR0227.md](https://www.ercotqueue.com/project/25INR0227.md)
- Source report: July 2026
- Site refresh: August 2026
- Methodology: [ERCOTQueue methodology](https://www.ercotqueue.com/methodology)
- License: [CC BY 4.0](https://creativecommons.org/licenses/by/4.0/)
- Source data (application/json): [https://www.ercotqueue.com/data/projects.json](https://www.ercotqueue.com/data/projects.json)

ERCOTQueue distinguishes reported source fields from independently derived analysis. Queue capacity records development and interconnection activity; it does not establish financing, construction, or commercial operation. Build Chance is a research signal, not a guarantee or investment recommendation.