Public dataset from ERCOTQueue

PJM cleared UCAP vs reliability requirement

PJM 27/28 BRA: 145,777 MW procured, 6,517 MW below requirement; 14.4% IRM vs 20% target.

Coverage: ERCOT, PJM, electricity, power markets, interconnection queue, capacity, energy data.

ERCOTQueue uses official public sources, identifies the source period, and separates reported facts from independent analysis.

Get the ERCOT Queue Monthly brief by email: one email per monthly ERCOT interconnection queue refresh. Research only, no pitch, unsubscribe any time.

Open the interactive ERCOTQueue page