ERCOT GIS Report: October 2026 Summary
The October 2026 ERCOT GIS report: 1,736 generation project rows totaling 445.9 GW. What changed this month, 12 months of totals, and where to download the report and processed data.
Latest report
Report: October 2026. Source file: GIS_Report_October_2026.xlsx.
- Project rows: 1,736 (−22 vs Sep 2026)
- Capacity: 445.9 GW (+7.4 GW vs Sep 2026)
- Active projects: 1,627
- Commissioned: 109
What changed since Sep 2026
- 36 new entries
- 65 projects no longer in the report
- 22 newly showing an interconnection agreement milestone
- 0 newly in construction
- 6 newly commissioned
Where to get the ERCOT GIS report
- ERCOT GIS report page (ercot.com)
- Processed CSV of every project row
- Processed JSON
- This summary as JSON
What the report contains
The workbook's project detail sheets, Large Gen and Small Gen, list each interconnection request by its INR number with fuel, capacity, county and zone, study and agreement milestones, and the projected commercial operation date. ERCOTQueue parses both sheets every month and keeps every report since December 2018.
The report records interconnection requests, not a supply forecast. Projects leave the queue every month.
Monthly totals
| Report | Project rows | Capacity | Row change |
|---|---|---|---|
| Oct 2026 | 1,736 | 445.9 GW | −22 |
| Sep 2026 | 1,758 | 438.5 GW | −20 |
| Aug 2026 | 1,778 | 438.0 GW | −19 |
| Jul 2026 | 1,797 | 439.9 GW | +4 |
| Jun 2026 | 1,793 | 433.7 GW | −9 |
| May 2026 | 1,802 | 426.5 GW | −7 |
| Apr 2026 | 1,809 | 420.8 GW | −37 |
| Mar 2026 | 1,846 | 425.5 GW | +14 |
| Feb 2026 | 1,832 | 417.7 GW | +1 |
| Jan 2026 | 1,831 | 415.4 GW | +21 |
| Dec 2025 | 1,810 | 407.4 GW | +1 |
| Nov 2025 | 1,809 | 399.8 GW | — |
Coverage: ERCOT, GIS report, Generation Interconnection Status, interconnection queue, Texas.
- Download source data (text/csv)
- Download source data (application/json)
- Download source data (application/json)
ERCOTQueue uses official public sources, identifies the source period, and separates reported facts from independent analysis.
Get the ERCOT Queue Monthly brief by email: one email per monthly ERCOT interconnection queue refresh. Research only, no pitch, unsubscribe any time.