Eagle Springs Storage
Eagle Springs Storage: 34 MW Battery project in Delta County, ERCOT NORTH developed by Eagle Springs BESS LLC. Currently IA + FIS complete; build-chance 85%. Independent ERCOT queue tracking by Matt Prusak.
Coverage: ERCOT, interconnection queue, Battery, power markets, energy data.
ERCOTQueue uses official public sources, identifies the source period, and separates reported facts from independent analysis.
Get the ERCOT Queue Monthly brief by email: one email per monthly ERCOT interconnection queue refresh. Research only, no pitch, unsubscribe any time.